The National Perspective Plan (NPP) was prepared by the then Ministry of Irrigation (now Ministry of Jal Shakti) in August 1980 for water resources development through inter basin transfer of water, for transferring water from water surplus basins to water-deficit basins. Under the NPP, the National Water Development Agency (NWDA) has identified 30 links (16 under Peninsular Component & 14 under Himalayan Component) for preparation of Feasibility Reports.

Issues related to funds allocation and utilization for Ken- Betwa Link project (KBLP) will come at the stage of implementation of the project.  A tripartite Memorandum of Agreement (MoA) for the implementation of the project jointly has been signed by the Hon’ble Union Minister for Jal Shakti and Hon’ble Chief Ministers of Madhya Pradesh and Uttar Pradesh on 22.03.2021 in the august presence of Hon’ble Prime Minister of India.

Details and status of the proposals for inter-state linking of rivers under the Inter Linking of Rivers Programme is furnished at Annexure-I.

Feasibility Report of Mahanadi (Barmul) –Godavari (Dowlaiswaram) Link project [an alternate to Mahanadi (Manibhadra) – Godavari (Dowlaiswaram)] was completed and circulated to the concerned States in October, 2020. Interlinking of Rivers projects depend entirely on according of consent by party States.

The river link schemes under ILR Programme have been formulated by considering all relevant engineering parameters like hydrological, meteorological, hydraulic, topographical, geological, geotechnical parameters and other factors like Socio – economic factors, Submergence issues, Environmental Impact Assessment factors and Rehabilitation and Resettlement issues etc.

This Information was given by the Minister of State for Jal Shakti, Shri Bishweswar Tudu in a written  reply in Rajya Sabha today.

*****

AnnexurE-I

Details and Status of the Proposals for Inter-State Linking of Rivers under the Inter Linking of Rivers Programme

S. No.

Name

Rivers

States concerned

Present Status

Peninsular Component

 

 

 

1

Mahanadi (Manibhadra) -Godavari (Dowlaiswaram) link

Mahanadi & Godavari

Odisha, Maharashtra, AP, MP, Telangana, Jharkhand, Karnataka, Chhattisgarh

FR Completed*

2

Godavari (Inchampalli) – Krishna (Pulichintala) link

Godavari & Krishna

Odisha, Maharashtra, AP, MP, Telangana, Karnataka, Chhattisgarh

FR Completed

3

Godavari (Inchampalli) – Krishna (Nagarjunasagar) link

Godavari & Krishna

-do-

FR Completed #

DPR Completed

4

Godavari (Polavaram) – Krishna (Vijayawada) link

Godavari & Krishna

-do-

FR Completed

5

Krishna (Almatti) – Pennar link

Krishna &Pennar

Maharashtra, Andhra Pradesh, Karnataka &Telangana

FR Completed

6

Krishna (Srisailam) – Pennar link

Krishna &Pennar

-do-

FR Completed

7

Krishna (Nagarjunasagar) – Pennar (Somasila ) link

Krishna &Pennar

-do-

FR Completed #

DPR Completed

8

Pennar (Somasila) – Cauvery (Grand Anicut) link

Pennar& Cauvery

Andhra Pradesh, Karnataka, Tamil Nadu, Kerala &Puducherry

FR Completed #

DPR Completed

9

Cauvery (Kattalai) – Vaigai -Gundar link

Cauvery,Vaigai&Gundar

Karnataka, Tamil Nadu, Kerala &Puducherry

DPR Completed

10

Ken-Betwa link

Ken &Betwa

Uttar Pradesh & Madhya Pradesh

DPR (Phase-I,II & Comprehensive report) Completed

11 (i)

Parbati -Kalisindh- Chambal link

Parbati, Kalisindh& Chambal

Madhya Pradesh, Rajasthan & Uttar Pradesh (UP requested to be consulted during consensus building)

FR Completed

(ii)

Parbati-Kuno-Sindh link

Parbati, Kuno and  Sindh

MP and Rajasthan

PFR completed $

12

Par-Tapi-Narmada link

Par, Tapi &

Narmada

Maharashtra & Gujarat

DPR Completed

13

Damanganga – Pinjal link

Damanganga &

Pinjal

Maharashtra & Gujarat

DPR Completed

14

Bedti – Varda link

Bedti &Varda

Maharashtra, Andhra Pradesh & Karnataka

PFR Completed

15

Netravati – Hemavati link

Netravati &

Hemavati

Karnataka, Tamil Nadu & Kerala

PFR Completed

16

Pamba – Achankovil – Vaippar link

Pamba, Achankovil& Vaippar

Kerala & Tamil Nadu,

FR Completed

* FR of alternate Mahanadi (Barmul) – Rushikulya – Godavari (Dowlaiswaram) link project completed

# Pending consensus on Manibhadra and Inchampalli dams, alternate study to divert unutilised waters of Godavari river carried out and DPR of Godavari (Inchampalli) – Pennar (Somasila)- Cauvery (Grand An-icut) link project completed.

$ Integration of Eastern Rajasthan Canal Project of Rajasthan and Parbati- Kalisindh-Chambal link.

Himalayan Component

1.

Manas-Sankosh-Tista-Ganga (M-S-T-G) link

Manas, Sankosh,  Tista and Ganga

Assam, West Bengal, Bihar& Bhutan

FR completed

2.

Kosi-Ghaghra link

Kosi & Ghaghra

Bihar , Uttar Pradesh & Nepal

PFR completed

3.

Gandak-Ganga link

Gandak& Ganga

-do-

FR completed

(Indian portion)

4.

Ghaghra-Yamuna link

Ghaghra &           Yamuna

-do-

FR completed (Indian portion)

5.

Sarda-Yamuna link

Sarda& Yamuna

Bihar, Uttar Pradesh, Haryana, Rajasthan, Uttarakhand& Nepal

FR completed (Indian portion)

6.

Yamuna-Rajasthan link

Yamuna &Sukri

Uttar Pradesh, Gujarat, Haryana & Rajasthan

Draft FR completed

7.

Rajasthan-Sabarmati link

Sabarmati

-do-

FR completed

8.

Chunar-Sone Barrage link

Ganga &Sone

Bihar & Uttar Pradesh

Draft FR completed

9.

Sone Dam – Southern Tributaries of Ganga link

Sone&Badua

Bihar & Jharkhand

PFR completed

10.

Ganga(Farakka)-Damodar-Subernarekha link

Ganga, Damodar & Subernarekha

West Bengal, Odisha & Jharkhand

FR completed

11.

Subernarekha-Mahanadi link

Subernarekha& Mahanadi

West Bengal & Odisha

FR completed

12.

Kosi-Mechi link

Kosi&Mechi

Bihar , West Bengal & Nepal

PFR completed

13.

Ganga (Farakka)-Sunderbans link

Ganga &Ichhamati

West Bengal

FR completed

14.

Jogighopa-Tista-Farakka link

(Alternative to M-S-T-G)

Manas, Tista&     Ganga

-do-

Dropped

 