- Production of Crude Oil
Crude oil production[1] during November,2020 was2486.01 TMT which is7.25% lower than target and4.91% lower when compared with November, 2019.Cumulative crude oil production during April-November, 2020 was 20426.50 TMT which is 5.28% and 5.98% lower than target for the period and production during corresponding period of last yearrespectively. Unit-wise and State-wise crude oil production is given at Annexure-I. Unit-wise crude oil production for the month of November, 2020 and cumulatively for the period April-November, 2020 vis-à-vis same period of last year has been shown in Table-1 and month-wise in Figure-1.
Table-1: Crude Oil Production (in TMT)
Oil Company |
Target |
November (Month) |
April-November (Cumulative) |
||||||
2020-21 (Apr-Mar) |
2020-21 |
2019-20 |
% over last year |
2020-21 |
2019-20 |
% over last year |
|||
Target |
Prod.* |
Prod. |
Target |
Prod.* |
Prod. |
||||
ONGC |
20931.54 |
1739.06 |
1647.62 |
1673.23 |
98.47 |
14022.87 |
13508.55 |
13638.31 |
99.05 |
OIL |
3268.00 |
273.97 |
243.20 |
260.17 |
93.47 |
2115.91 |
1985.34 |
2147.01 |
92.47 |
PSC Fields |
8265.00 |
667.41 |
595.19 |
680.91 |
87.41 |
5426.93 |
4932.62 |
5939.42 |
83.05 |
Total |
32464.53 |
2680.44 |
2486.01 |
2614.31 |
95.09 |
21565.71 |
20426.50 |
21724.74 |
94.02 |
Note: 1. Target for the year 2020-21 is provisional, subject to finalization. *: Provisional
2. Totals may not tally due to rounding off.
Figure-1: Monthly Crude Oil Production
Unit-wise production details with reasons for shortfall are as under:
-
- Crude oil production by ONGC in nomination block during November, 2020 was 1647.62 TMT which is 5.26%lower than target and1.53%lower when compared with November 2019. Cumulative crude oil production by ONGC during April-November, 2020 was 13508.55 TMT which is 3.67%and 0.95% lower than target for the period andproduction during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Production planned from WO-16 cluster could not be realized due to delay in MOPU (Sagar Samrat) as activities at GPC yard Abu Dhabi got affected due to COVID restrictions/lockdown
- Production planned from new wells in Ratna field affected due to non- availability of ESPs (electrical submersible pumps) for well completion due to implications of COVID-19
- New wells planned under Cluster-8 development project delayed due to toppling of D-30-2 platform jacket during installation and further delay in installation of new platforms due to COVID implications
-
- Crude oil production by OIL in the nominationblock during November, 2020 was243.20 TMT which is 11.23% lower than the monthly target and 6.53% lower than the November, 2019. Cumulative crude oil production by OIL during April-November, 2020 was 1985.34 TMT which is 6.17% and 7.53% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Less than planned contribution from workover wells, drilling wells and old wells.
- Bandhs /blockade by local people and associations etc. after the Baghjan Blowout, protests/agitation etc.
-
- Crude oil production by Pvt/JVscompanies in the PSC (production sharing contract) regime during November, 2020 was 595.19 TMT which islower by 10.82% than the monthly target and 12.59%lowerthanNovember, 2019.Cumulative crude oil production by Pvt/JVs companies during April-November, 2020 was 4932.62 TMT which is 9.11% and 16.95% lower than target for the period and production during corresponding period of last year respectively.Reasons for shortfall in production are as under:
- RJ-ON-90/1 (CEIL): (1) Mangla–Shortfall in production due to reasons inter-alia failure of hydraulic submersible pump, delay in hook up of new injectors (Mangala), delayed start-up of polymer injection (Aishwarya), high water cut (Saraswati), ceasing of flow (Guda).
- CB-ONN-2003/1 (ONGC): Production is less due to COVID-19 situation, rig mobilization got delayed resulting in Drilling of new wells and less crude offtake.
- CB-ONN-2004/2 (ONGC): Development wells could not be drilled as planned in Q1 & Q2 FY2020-21 respectively.
- CB-ONN-2000/1 (GSPC):Lower production due to reservoir issues and shut in of wells.
- Production of Natural Gas
Natural gas production during November,2020 was 2331.25MMSCM which is 20.56% lower than the monthly target and 9.06% lower when compared with November, 2019. Cumulative natural gas production during April-November, 2020 was 18704.02MMSCM which is 14.79% and 11.81% lower than target for the period and production during corresponding period of last year respectively. Unit-wise and state-wise natural gas production is given at Annexure-II. Unit-wise natural gas production for the month of November, 2020 and cumulatively for the period April-November, 2020 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.
Table-2: Natural Gas Production (inMMSCM)
Oil Company |
Target |
November (Month) |
April-November (Cumulative) |
||||||
2020-21 (Apr-Mar) |
2020-21 |
2019-20 |
% over last year |
2020-21 |
2019-20 |
% over last year |
|||
Target |
Prod.* |
Prod. |
Target |
Prod.* |
Prod. |
||||
ONGC |
24437.08 |
2005.53 |
1823.53 |
1893.85 |
96.29 |
16299.03 |
14686.59 |
15919.91 |
92.25 |
OIL |
3181.54 |
276.29 |
203.91 |
228.20 |
89.36 |
2126.41 |
1668.20 |
1851.81 |
90.08 |
PSC Fields |
6826.82 |
652.73 |
303.81 |
441.36 |
68.84 |
3524.72 |
2349.23 |
3437.85 |
68.33 |
Total |
34445.44 |
2934.54 |
2331.25 |
2563.40 |
90.94 |
21950.17 |
18704.02 |
21209.56 |
88.19 |
Note: 1. Target for the year 2020-21 is provisional, subject to finalization. *: Provisional
2. Totals may not tally due to rounding off.
Figure-2: Monthly Natural Gas Production
-
- Natural gas production by ONGC in the nominationblocks during November, 2020 was 1823.53MMSCM which is 9.07% lower than target and 3.71% lower when compared with November 2019. Cumulative natural gas production by ONGC duringApril-November, 2020 was 14686.59 MMSCM which is 9.89% and 7.75% lower than target for the period and production during corresponding period of last year respectively.Reasons for shortfall in production are as under:
- Closure of Gas wells in western offshore due to Hazira Plant shutdown on 24.09.20 and subsequent normalization.
- Less Gas production from WO16 cluster due to delay in Mobile Offshore Production Unit (MOPU) and non-realization of gain planned from new subsea wells in Bassein field due to delay in subsea umbilical connections/hook up jobs in view of Covid-19 implications.
- Less than planned production from Vasistha/S1 wells in EOA (Eastern Offshore Assets) due certain reservoir related issues.
-
- Natural gas production by OILin the nomination block during November, 2020 was 203.91 MMSCM which is 26.20% lower than monthly target and 10.64% lower than November, 2019. Cumulative natural gas production by OIL during April-November, 2020 was 1668.20 MMSCM which is 21.55% and 9.92% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Low upliftment/demand of gas by the major customers.
- Bandhs /blockade by local people and associations etc. after the Baghjan Blowout, protests/agitation etc.
-
- Natural gas production by Pvt/JVs companiesin the PSC (production sharing contracts) regime during November,2020 was 303.81MMSCM which is 53.46% lowerthan monthly target and31.16% lower than November, 2019. Cumulative natural gas production by Pvt/JVs during April-November, 2020 was 2349.23MMSCM which is 33.35% and 31.67% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- KG-DWN-98/3 (RIL): Impact of COVID on project progress of R-Series D-34 field of KG-DWN-98/3 and efforts are being made for its start-up.
- RJ-ON/6 (FEL): Reduced gas offtake by Power Plant customer with Gas turbine in shut down.
- RJ-ON-90/1 (CEIL): RDG – Delay in new RDG plant start up due to Covid-19.
- KG-DWN-98/2 (ONGC): Well U3-B is producing less than the estimated profile and well is flowing with lower choke due to increase in water cut.
- Raniganj East (ESSAR): Production curtailed due delay in GAIL Pipeline & limited sales off-take and to avoid flaring.
- Crude Oil Processed (Crude Throughput)
Crude Oil Processed during November, 2020 was 20781.77TMT which is 1.57% higher than the target for the month but5.11% lower when compared with November, 2019. Cumulative crude throughput during April-November, 2020 was139337.10 TMT which is 15.94% and 17.82% lower than target for the period and crude throughput during corresponding period of last year respectively. Refinery-wise details of the crude throughput and capacity utilization during the month of November, 2020 vis-à-vis November, 2019 are given at Annexure-III and Annexure-IV. Company-wise crude throughput for the month of November, 2020 and cumulatively for the period April-November, 2020vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.
Table 3: Crude Oil Processed (Crude Throughput) (in TMT)
Oil Company |
Target |
November (Month) |
April-November (Cumulative) |
||||||
2020-21 (Apr-Mar) |
2020-21 |
2019-20 |
% over last year |
2020-21 |
2019-20 |
% over last year |
|||
Target |
Prod.* |
Prod. |
Target |
Prod.* |
Prod. |
||||
CPSE |
148031.12 |
12223.69 |
12191.32 |
12572.54 |
96.97 |
96410.26 |
77587.58 |
96230.25 |
80.63 |
IOCL |
72499.86 |
6049.23 |
6209.68 |
6090.08 |
101.96 |
47700.91 |
38771.00 |
46952.98 |
82.57 |
BPCL |
30499.95 |
2629.42 |
2584.71 |
2700.98 |
95.70 |
20518.21 |
15365.83 |
20585.96 |
74.64 |
HPCL |
17867.47 |
1067.63 |
1419.24 |
1520.37 |
93.35 |
11175.45 |
10741.22 |
11393.18 |
94.28 |
CPCL |
9000.00 |
900.00 |
729.45 |
788.63 |
92.50 |
5370.00 |
4838.02 |
6688.48 |
72.33 |
NRL |
2700.00 |
222.00 |
230.12 |
118.71 |
193.85 |
1804.00 |
1730.72 |
1759.48 |
98.37 |
MRPL |
15400.00 |
1350.00 |
1011.44 |
1346.26 |
75.13 |
9800.00 |
6089.40 |
8791.63 |
69.26 |
ONGC |
63.83 |
5.42 |
6.69 |
7.53 |
88.82 |
41.69 |
51.39 |
58.55 |
87.78 |
JVs |
14772.00 |
640.00 |
1631.92 |
1730.29 |
94.31 |
9175.00 |
10871.81 |
13141.41 |
82.73 |
BORL |
7800.00 |
640.00 |
593.93 |
657.83 |
90.29 |
5200.00 |
3666.24 |
5103.57 |
71.84 |
HMEL |
6972.00 |
0.00 |
1038.00 |
1072.46 |
96.79 |
3975.00 |
7205.57 |
8037.85 |
89.65 |
Private |
89515.16 |
7597.78 |
6958.53 |
7597.78 |
91.59 |
60183.37 |
50877.70 |
60183.37 |
84.54 |
RIL |
68894.99 |
5939.81 |
5482.03 |
5939.81 |
92.29 |
46340.49 |
39922.60 |
46340.49 |
86.15 |
NEL |
20620.18 |
1657.97 |
1476.50 |
1657.97 |
89.05 |
13842.89 |
10955.10 |
13842.89 |
79.14 |
TOTAL |
252318.28 |
20461.47 |
20781.77 |
21900.62 |
94.89 |
165768.63 |
139337.10 |
169555.04 |
82.18 |
Note: 1. Target for the year 2020-21 is provisional, subject to finalization. *: Provisional
2. Totals may not tally due to rounding off.
Figure 3: Crude Oil Processed (Crude Throughput)
3.1 CPSE Refineries’ crude oil processed during November, 2020 was 12191.32TMT which is marginally lower by 0.26% than the target for the month and3.03%lowerwhen compared with November, 2019.Cumulative crude throughputby CPSE refineries during April-November, 2020 was 77587.58TMT which is 19.52% and 19.37% lower than target for the period and crude throughputduring corresponding period of last year respectively.Reasons for shortfall in production are as under:
- IOCL-Koyali& Mathura: Crude processed regulated for low product demand due to COVID impact.
- IOCLK-Digboi: Crude processed lower due to planned shutdown deferred.
- BPCL-Kochi: Crude processed lower due to emergency shutdown of VGO Hydro-treater Unit.
- HPCL-Mumbai: Crude processed lower due to unplanned shutdown of secondary units.
- CPCL-Manali & MRPL-Mangalore: Crude processed lower due to Lower demand due to impact of COVID-19 lockdown.
- NRL-Numaligarh: Crude processed lower due to in line with domestic allocation.
3.2 JV refineries’ crude oil processed during November, 2020 was 1631.92TMT which is 154.99% higher than the target for the month but 5.69% lower when compared with November, 2019. Cumulative crude throughput during April-November, 2020 was10871.81 TMT which is 18.49% higher than target for the period but17.27% lower when compare with the corresponding period of last year respectively.
3.3 Private refineries’ crude oil processed during November, 2020 was 6958.53TMT which is 8.41% lower than the corresponding month of last year. Cumulative crude throughputduring April-November, 2020 was 50877.70 TMT which is 15.46% lower than thecorresponding period of last year.
- Production of Petroleum Products
Production of Petroleum Products during November, 2020 was 21425.49 TMT which is 1.79% higher than the target for the month but 4.83% lower when compared with November, 2019. Cumulative production during April-November, 2020 was 147590.55 TMT which is 12.89% and 14.87% lower than target for the period and production during corresponding period of last year respectively. Unit-wise production of petroleum products is given at Annexure-V. Company-wise production for the month of November, 2020 and cumulatively for the period April-November, 2020 vis-à-Vis same period of last year has been shown in Table-4 and month-wise in Figure-4.
-
- Production of petroleum Products by Oil’s Refineries during November, 2020 was 21047.82 TMT which is 1.93% higher than the target for the month but 4.82% lower when compared with November, 2019. Cumulative production of petroleum products by refineries during April-November, 2020 was 144762.79 TMT which is 12.96% and 14.94% lower than target for the period and production during corresponding period of last year respectively.
-
- Production of petroleum Products by Fractionators during November, 2020 was 377.68 TMT which is 5.67% lower than the target for the month and 5.73% lower when compared with November, 2019. Cumulative production by Fractionators during April-November, 2020 was 2827.76 TMT which is 9.13% and 11.12% lower than target for the period and production during corresponding period of last year respectively.
Table 4: Production of Petroleum Products (TMT)
Oil Company |
Target |
November (Month) |
April-November (Cumulative) |
||||||
2020-21 (Apr-Mar) |
2020-21 |
2019-20 |
% over last year |
2020-21 |
2019-20 |
% over last year |
|||
Target |
Prod.* |
Prod. |
Target |
Prod.* |
Prod. |
||||
CPSE |
139203.86 |
11496.63 |
11512.94 |
11860.20 |
97.07 |
90701.66 |
73499.48 |
90669.39 |
81.06 |
IOCL |
68912.87 |
5747.30 |
5899.48 |
5810.17 |
101.54 |
45335.10 |
37164.70 |
44640.70 |
83.25 |
BPCL |
28965.13 |
2501.41 |
2474.28 |
2603.91 |
95.02 |
19501.93 |
14752.21 |
19517.69 |
75.58 |
HPCL |
16438.97 |
976.36 |
1336.30 |
1369.33 |
97.59 |
10278.97 |
10003.08 |
10556.45 |
94.76 |
CPCL |
8278.87 |
835.00 |
690.61 |
705.09 |
97.95 |
4910.99 |
4447.30 |
6128.25 |
72.57 |
NRL |
2660.91 |
218.71 |
239.74 |
111.13 |
215.74 |
1778.80 |
1758.40 |
1698.07 |
103.55 |
MRPL |
13887.11 |
1212.76 |
866.12 |
1253.50 |
69.10 |
8856.69 |
5324.51 |
8073.61 |
65.95 |
ONGC |
60.00 |
5.10 |
6.42 |
7.08 |
90.65 |
39.19 |
49.28 |
54.63 |
90.21 |
JVs |
13590.40 |
570.92 |
1495.05 |
1670.89 |
89.48 |
8421.60 |
10107.24 |
12333.57 |
81.95 |
BORL |
6958.40 |
570.92 |
531.43 |
608.03 |
87.40 |
4639.60 |
3191.20 |
4671.42 |
68.31 |
HMEL |
6632.00 |
0.00 |
963.62 |
1062.86 |
90.66 |
3782.00 |
6916.05 |
7662.15 |
90.26 |
Private |
102154.50 |
8581.66 |
8039.83 |
8581.66 |
93.69 |
67185.50 |
61156.07 |
67185.50 |
91.03 |
RIL |
82374.12 |
7042.15 |
6536.54 |
7042.15 |
92.82 |
53958.26 |
50562.50 |
53958.26 |
93.71 |
NEL |
19780.38 |
1539.50 |
1503.28 |
1539.50 |
97.65 |
13227.24 |
10593.57 |
13227.24 |
80.09 |
Total Refinery |
254948.76 |
20649.21 |
21047.82 |
22112.74 |
95.18 |
166308.77 |
144762.79 |
170188.47 |
85.06 |
Fractionators |
4572.73 |
400.36 |
377.68 |
400.62 |
94.27 |
3111.84 |
2827.76 |
3181.64 |
88.88 |
TOTAL |
259521.49 |
21049.57 |
21425.49 |
22513.36 |
95.17 |
169420.61 |
147590.55 |
173370.11 |
85.13 |
Note: 1. Target for the year 2020-21 is provisional, subject to finalization. *: Provisional
2. Totals may not tally due to rounding off.
Figure 4: Monthly Refinery Production of Petroleum Products
[1]Including condensate
Click here to see Annexure-III
******